On Wednesday I went to Carrollton and Douglasville to do the following maintenance and work orders in the building.

Checked the sound system, satellite, pulpit control and fuse and all were working properly. (completed)

I received a phone call from Chris Curby and was asked to deliver some ceiling tile adhesive to Douglasville. (completed)

Checked all the lights in the attic and all is working good. (completed)

FBJ28998 Repaired the Relief Society door with wood putty in the inside edge of the door and stained it. (completed)

Repaired the rubber trim on the top of the Relief Society door with glue. (completed)

The fire alarm system checked out good. (completed)

Checked all the fire extinguishers in the building and signed and dated the cards. All had a full charge. (completed)

Worked 8 hours

Jeff








Checked the sound system, satellite, pulpit control and fuse and all were working properly. (completed)



Checked smoke detectors through out the building and all are working properly. (completed)


I went to Douglasville to deliver some ceiling tile adhesive for Chris Curby. (completed)



Checked all the lights in the attic and all is working good, (completed)



FBJ28998 Repaired the door with wood putty and stained it. (completed)



Repaired the rubber trim on the door with glue. (completed)



The fire alarm system checked out good. (completed)



Checked all the fire extinguishers in the building and signed and dated the cards. All had a full charge. (completed)