On Tuesday Chris and I went to Cartersville to perform the following work.
FBJ13584 Installed and painted the insulation on the outside of all condenser HVAC lines as needed and is completed.
FBJ28625 Tested and checked all HVAC systems through out the building and they are operating properly.
Checked all the high lights in the chapel and cultural hall and had to replace one fluoresent bulb in the chapel.
Checked the sound system and the Satellite system. The sound system was not working right, there was a bad switch, it would not turn off and Chris said he will call someone to fix it. The satellite system was working properly.
We organized the outside storage shed area.
Two outside doors were loose and I had to readjust the striker plate for them to close tighter. Checked all the door closers and hardware and touched up doors with stain as needed.
Worked 8 hours to complete work.
Jeff