On Thursday I went to help Bobby to the following work in the Glenridge Church.

I originally took some of the ceiling tiles out of the Library to match the tiles in the Primary Room, then I had to measure and cut to replace the extra ones back in the Library. (completed)

I had to measure and cut different sizes of tiles to replace them in the ceiling in the Primary Room to fit properly. (completed)

I had to measure and cut different sizes of tiles to replace them in the ceiling in rooms 123, 124 and 125. (completed)

I had to measure and cut different sizes of tiles to replace them in the ceiling in rooms 116,117 and 118 (completed)

I replaced the ceiling tiles in room 126, 127 and 128 with new ones. I had to measure and cut the tiles to fit properly. (completed)


Worked 9 hours

Jeff









I originally took some of the ceiling tiles out of the Library to match the tiles in the Primary Room, then I had to measure and cut to replace the extra ones back in the Library. (completed)





I had to measure and cut different sizes of tiles to replace them in the ceiling in the Primary Room to fit properly. (completed)





I had to measure and cut different sizes of tiles to replace them in the ceiling in rooms 123, 124 and 125. (completed)









I had to measure and cut different sizes of tiles to replace them in the ceiling in rooms 116,117 and 118 (completed)






I replaced the ceiling tiles in room 126, 127 and 128 with new ones. I had to measure and cut the tiles to fit properly. (completed)