FBJ31777 room 117 and FBJ31780 room 114 ceiling tiles have been painted with white paint to match the tiles. (completed)
FBJ31789 I had to use the giant ladder to repair the crack in the ceiling around the projection screen with joint compound. (completed)
I lubricated the pulpit control and checked the fuse, satellite and sound system and they sound good.
I checked the baby changing tables and tightened the screws as needed to secure it to the walls.
I checked the won doors in the chapel and classrooms and they were all opening and closing properly.
FBJ31783 I repaired the loose spout in the font by caulking it and sealing it to the wall. So, the water will not get back on the wall. (completed)
FBJ31787 Billy made the roof repairs around the speakers in the cultural hall. I was able to spray the tiles with kilz to seal it and I went back over it with white paint. The sim card did not allow me to take an after picture. I will take a picture of it the next time I am in the building. (completed)
FBJ31785 I had added joint compound in the Primary room corners. I will have to do the RS room the next time I am in the building.
The sim card stopped working so I was not able to take pictures of the following work. On my way home I did get another sim card to be ready for tomorrow's pictures.
FBJ31784 I had water to the drains in the mezzanine. (completed)
FBJ31786 I found the missing cover and replaced it back on the sprinkler head in room 103 and 105 last week. (completed)
FBJ31756 I verify the sealing on the asphalt was done by Asphalt Enterprises. (completed)
FBJ30367 The thermostat control for the nursery and material center is located in room 115 to control the A/C unit. I checked the air and it doesn't seem to be blowing as cold as it should be.
FBJ31759 Billy had repaired the roof leak in the cultural hall ceiling. I sprayed kilz over the stain and went back over it with white paint. (completed)
Worked 8 hours,
Jeff
FBJ31777 room 117 and FBJ31780 room 114 ceiling tiles have been painted with white paint to match the tiles. (completed)
FBJ31789 I had to use the giant ladder to repair the crack in the ceiling around the projection screen with joint compound. (completed)
I lubricated the pulpit control and checked the fuse, satellite and sound system and they sound good.
I checked the baby changing tables and tightened the screws as needed to secure it to the walls.
I checked the won doors in the chapel and classrooms and they were all opening and closing properly.
FBJ31783 I repaired the loose spout in the font by caulking it and sealing it to the wall. So, the water will not get back on the wall. (completed)
FBJ31787 Billy made the roof repairs around the speakers in the cultural hall. I was able to spray the tiles with kilz to seal it and I went back over it with white paint. The sim card did not allow me to take an after picture. I will take a picture of it the next time I am in the building. (completed)
FBJ31785 I had added joint compound in the Primary room corners. I will have to do the RS room the next time I am in the building.
No comments: