Thursday, July 21, 2011

07.21.11 Cedartown

I went to Cedartown on Thursday to do the following work orders and maintenance work in the building.

FBJ32208 I had to sand and paint the drywall around the sensor in room 101. (Completed)

I noticed there was a hole that had been cut in the wall in room 101 and I had to patch it with sheetrock mud. I need to let it dry so, the next time I go there I will have to re-mud, sand and paint it.

FBJ32211 There was a few ceiling tiles in the closet that I was able to use to replace a few of the tiles in the hallway. The other ceiling tiles that had little nicks I touched up with sheetrock mud. I went to Home Depot to get the more to match the tiles in room 102 and 107 but they were out. The sales person said they will order more and the next time I go I will be able continue the work.

The lights in the chapel and cultural hall are working good.

I lubricated the pulpit control and checked the fuse and sound system and they sound good. The satellite did not have a signal.

FBJ32212 In the serving area (kitchen) their was a mouse hole in the ceiling and I replaced the ceiling tile. I also noticed a crack in one of the ceiling tiles and touched it up with sheetrock mud. (completed)

FBJ32207 The key that was in the key box would not open the door to M101. I was not able to check out the door that was hard to close.

FBJ32213 I patched the small hole in the font wall and it needs to dry before I can paint it the next time I go there.


Worked 8 hours,

Jeff








FBJ32208 I had to sand and paint the drywall around the sensor in room 101. (Completed)





I noticed there was a hole that had been cut in the wall in room 101 and I had to patch it with sheetrock mud. I need to let it dry so, the next time I go there I will have to re-mud, sand and paint it.
























FBJ32211 There was a few ceiling tiles in the closet that I was able to use to replace a few of the tiles in the hallway. The other ceiling tiles that had little nicks I touched up with sheetrock mud. I went to Home Depot to get the more to match the tiles in room 102 and 107 but they were out. The sales person said they will order more and the next time I go I will be able continue the work.






The lights in the chapel and cultural hall are working good.





I lubricated the pulpit control and checked the fuse and sound system and they sound good. The satellite did not have a signal.






FBJ32212 In the serving area (kitchen) their was a mouse hole in the ceiling and I replaced the ceiling tile. I also noticed a crack in one of the ceiling tiles and touched it up with sheetrock mud. (completed)