On Friday I went to the Calhoun building to do the following work orders and maintenance work.

I checked the lights and the HVAC filters in the attic and all is working properly and looks good.

FBJ30076 The parts are still on order and have not arrived for the light pole.

I checked the won doors through out the building and they are all opening and closing properly. The handles are good and tight and they are latching properly.

FBJ30366 Still waiting on the piano cover to arrive.

Lubricated the pulpit control and checked the fuse and sound system and they sound good. But the satellite is not giving a signal in the chapel.

The chapel lights are all lit up and no burnt bulbs were found.

The baby changing tables were good and tightly secured to the walls.

The women's and men's restrooms toilets flushed with no problems and all other plumbing was working properly, no leaks found.

The kitchen appliances were all working properly and no leaks were found with the plumbing under the sink.

FBJ32484 The Safety and Health Inspection Form was completed in the Calhoun Building. It will be faxed to Debbie on Monday. (completed)

I tested the vacuum cleaners and they were working properly.

I had to tighten the screws on the legs on a few classroom tables for them to be secured to the bottom of the table.

I had to replace a ballast on the light in the room 102.

I had to adjust the strike plate on the exterior door on the right side of the building to make it shut good and tight. I checked all others and they are shutting properly.

Today I noticed there is an extra key on the keyring in the key box that opens the two doors of the electrical rooms.

Worked 8 hours,

Jeff






I checked the lights and the HVAC filters in the attic and all is working properly and looks good.





FBJ30076 The parts are still on order and have not arrived for the light pole.






I checked the won doors through out the building and they are all opening and closing properly. The handles are good and tight and they are latching properly.





FBJ30366 Still waiting on the piano cover to arrive.






Lubricated the pulpit control and checked the fuse and sound system and they sound good. But the satellite is not giving a signal in the chapel.






The chapel lights are all lit up and no burnt bulbs were found.






The baby changing tables were good and tightly secured to the walls.












The women's and men's restrooms toilets flushed with no problems and all other plumbing was working properly, no leaks found.







The kitchen appliances were all working properly and no leaks were found with the plumbing under the sink.





FBJ32484 The Safety and Health Inspection Form was completed in the Calhoun Building. It will be faxed to Debbie on Monday. (completed)





I tested the vacuum cleaners and they were working properly.






I had to tighten the screws on the legs on a few classroom tables for them to be secured to the bottom of the table.






I had to replace a ballast on the light in the room 102.





I had to adjust the strike plate on the exterior door on the right side of the building to make it shut good and tight. I checked all others and they are shutting properly.