On Friday I went to Kennesaw to do the following work orders and maintenance work in the building.

FBJ29996 The curtains have not been repaired yet.

FBJ32262 I checked the organ and it played, it seemed to have been repaired. (completed)

I lubricated the pulpit control and checked the fuse, satellite and sound system and they sound good.

The lights in the chapel and cultural hall are working properly.

I checked the won-doors, they opened, closed and latched properly.

FBJ32731
This building has natural gas (item #1019) and has underground metallic gas piping.
When you go into the men's restroom you go to the second door and you will enter the baptismal font and turn left you will walk into the font. The light switch is on the right side of the door on the wall as you enter in to the font. There is another door to enter the font from the RS room that is located in the front and the Caution sign is on the outside of the RS door.
When you go into the women's restroom you go to the second door and you will enter the baptismal font and turn right you will walk into the font. The light switch is on the left side of the door on the wall as you enter in to the font. There is another door to enter the font from the RS room that is located in the front and the Caution sign is on the outside of the RS door.
There were no Sloan flushmate toilets in the restrooms. (completed)

I checked the thermostat controls through out the building and they were all working properly blowing cool air.

I checked the exterior doors through out the building and had to adjust the strike plate on one the doors for it to close tight and all other doors are opening and closing properly.

FBJ32807 There was a bag over the first toilet in the women's restroom that was clogged. There was lots and lots of toilet paper in the toilet, so I had to put some gloves on to take it all out. Then I plunged and plunged it real good until it was unclogged and clear water was visible. I flushed it a few times after to be sure it was working properly. I also checked the other plumbing and found no leaks.(completed)

The plumbing and toilets in the men's restroom were all working properly, no leaks were found.

I checked the baby changing tables and had to tighten the screws as needed to secure them tightly to the walls.

I checked the basketball goals by turning the switch on to lower and rise them back up and both are working properly.

I checked the outlets through out the building and they all tested good.

I checked and tightened the legs on the classroom tables as needed for them to be secured to the bottom of the tables.

worked 8 hours,

Jeff








FBJ29996 The curtains have not been repaired yet.





FBJ32262 I checked the organ and it played, it seemed to have been repaired. (completed)






I lubricated the pulpit control and checked the fuse, satellite and sound system and they sound good.






The lights in the chapel and cultural hall are working properly.






I checked the won-doors, they opened, closed and latched properly.





FBJ32731 This building has natural gas (item #1019) and has underground metallic gas piping. (completed)





I checked the thermostat controls through out the building and they were all working properly blowing cool air.






I checked the exterior doors through out the building and had to only adjust one of the strike plates on the door for it to close tight and all other doors are opening and closing properly.








FBJ32807 There was a bag over the first toilet in the women's restroom that was clogged. There was lots and lots of toilet paper in the toilet, so I had to put some gloves on to take it all out. Then I plunged and plunged it real good until it was unclogged and clear water was visible. I flushed it a few times after to be sure it was working properly. I also checked the plumbing and found no leaks.(completed)






The plumbing and toilets in the men's restroom were all working properly, no leaks were found.







I checked the baby changing tables and had to tighten the screws as needed to secure them tightly to the walls.







FBJ32731 When you go into the men's restroom you go to the second door and you will enter the baptismal font and turn left you will walk into the font. The light switch is on the right side of the door on the wall as you enter in to the font. There is another door to enter the font from the RS room that is located in the front and the Caution sign is on the outside of the RS door. (completed)







FBJ32731 When you go into the women's restroom you go to the second door and you will enter the baptismal font and turn right you will walk into the font. The light switch is on the left side of the door on the wall as you enter in to the font. There is another door to enter the font from the RS room that is located in the front and the Caution sign is on the outside of the RS door. (completed)






I checked the basketball goals by turning the switch on to lower and rise them back up and both are working properly.





I checked the outlets through out the building and they all tested good.






I checked and tightened the legs on the classroom tables as needed for them to be secured to the bottom of the tables.