I repaired the door in the women's restroom because it would not shut. I had to drill four new holes and remount the cylinder back on the door for it to shut properly.
The water fountain handle was broke off and I had to re-brace it and glue it back together for it to work properly.
I was asked to check the projector screens in the gym. I checked both sides by putting them down and back up and they are working properly.
I noticed in the RS room that the string was pulled out of the rod and I had to pull the string back through the rod and adjust it on the opposite end, then pull the string back down and put it back in the hanger. I had to attached the hanger on the wall for it work properly.
The piano bench leg was about to fall out, so I had to tighten the screw on the leg, then put the leg back on the bench and tighten the nut.
I checked the outlets through the building and they all tested good.
I checked the lights in the chapel, cultural hall and hall ways. There was two spots lights burnt out in the chapel that I changed using the long extension pole and put two new bulbs. There was a light out in the back entrance in the hallway that I had to change the ballast and put two new bulbs. All other lights are working good.
worked 8 hours,
Jeff
I repaired the door in the women's restroom because it would not shut. I had to drill four new holes and remount the cylinder back on the door for it to shut properly.
The water fountain handle was broke off and I had to re-brace it and glue it back together for it to work properly.
I was asked to check the projector screens in the gym. I checked both sides by putting them down and back up and they are working properly.
I noticed in the RS room that the string was pulled out of the rod and I had to pull the string back through the rod and adjust it on the opposite end, then pull the string back down and put it back in the hanger. I had to attached the hanger on the wall for it work properly.
The piano bench leg was about to fall out, so I had to tighten the screw on the leg, then put the leg back on the bench and tighten the nut.
I checked the outlets through the building and they all tested good.
I checked the lights in the chapel, cultural hall and hall ways. There was two spots lights burnt out in the chapel that I changed using the long extension pole and put two new bulbs. There was a light out in the back entrance in the hallway that I had to change the ballast and put two new bulbs. All other lights are working good.