FBJ28618 In the Decatur building I installed the locks on the clerk file under the counter. Chris had the locks, so I did not have to purchase them. I had to measure the area to drill the holes in the right place on the door to install the locks. (completed)
FBJ28630 Then I went to Stockbridge to replaced the broken ceiling tile in room 111. I did not have to purchase a new tile, there was one outside in the shed. (completed)
FBJ28762 Installed two locks on the 2 upper cabinets on the left side doors in the clerk's office. Locks did not have to be purchased. (completed)
The bottom cabinet with 2 big drawers needed locks, but they need a different type of lock to make it lock properly. At a later time I will have to figure out and purchase the correct lock to make it work. (not completed)
No pictures were taken, I will take them once I complete the work.
FBJ28850 Checked the freezer and cleaned the coil. The leakage was from a water jug inside the refrigerator that had spilled water onto the floor. Moved the refrigerator away from the wall, cleaned it and it is working properly. (completed)
Time allowed me to touch up a couple of doors with stain in the hallway that had some scratches and chips. (completed)
Worked 8 hours
Jeff
FBJ28618 Installed the locks on clerk file under the counter. (completed)
FBJ28630 Replaced broken ceiling tile in room 111 (completed)
FBJ28850 Checked the freezer and cleaned the coil, it is working properly. (completed)
Time allowed me to touch up the woodwork on the doors with stain in the hallway. (completed)