I had to change the door stop in the culture hall, the rubber end had broke off. (completed)
In the men's restroom there was a leak in the tank of the toilet and I had to tighten the two screws on the back to seal the rubber gaskets that were loose to stop it from leaking. (completed)
Checked, signed and dated one of the fire extinguisher and the other one was checked but it was locked in the cabinet so I could not sign or date it. (not completed)
Checked the fuse and greased the pulpit control in the chapel and it is working properly. (completed)
Checked the sound system and satellite in the chapel, no problems were found. (completed)
Checked the lights in the hall way and no bulbs were burnt all is working properly. (completed)
One of the handles on the accordion door is broken off and I have the hardware for it, the screws and bolts are broken off and the rollers are hanging up real bad on the top. It is difficult to side both doors back and forth, it needs to be serviced with the company that installed it. (not completed)
The cultural hall has a tear in the carpet and I need to speak with Debbie Woodruff to see what steps need to be taken to repair it. (not completed)
The ballast in the men's restroom was replaced and needed a new fluorescent light bulb. The bulb was replace, but no after picture was taken. (completed)
Checked the doors through out the building and had to adjust the strike plates on 3 of the doors for them to shut tight. (completed)
Checked the thermostat for heating and HVAC system through out the building and no problems were found, all is working good. (Completed)
Worked 8 hours
Jeff
I had to change the door stop, the rubber end had broke off. (completed)
There was a leak on the tank of the toilet and I had to tighten the two screws that were loose to stop it from leaking. (completed)
Checked, signed and dated one of the fire extinguisher and the other one was checked but it was locked in the cabinet so I could not sign or date it. (not completed)
Checked the fuse and greased the pulpit control and it is working properly. (completed)
Checked the sound system and satellite in the chapel, no problems were found. (completed)
Checked the lights in the hall way and all is working properly. (completed)
One of the handles on the accordion door is broken off and I have the hardware for it, the screws and bolts are broken off and the rollers are hanging up real bad on the top. It is difficult to side back and forth, it needs to be serviced with the company that installed it. (not completed)
The cultural hall has a tear in the carpet and I need find out what steps need to be taken to repair it. (not completed)
The ballast in the men's restroom was replaced and needed a new fluorescent light bulb. The bulb was replace, but no after picture was taken. (completed)
Adjusted the strike plates on 3 of the doors in the building for them to shut tight. (completed)
Checked the thermostat for heating and HVAC system and it is working good. (Completed)