FBJ29757 I was able to repair the outlet shortage by tightening the loose wire on the inside of the outlet, by the custodial room. (completed)
I checked the thermostat controls in the building and all were working good with cool air.
FBJ29765 The cracked pipe in the parking lot facing the road had to be repaired by cutting about 3 inches off the end of the pipe where it was cracked. (completed)
I checked the screws on the changing tables and they are all good and tight to the wall.
FBJ29443 I checked the won-door handles and it is not repaired. Does Dave Stickel need to be call again?
FBJ29024 I noticed the carpet in the hallway and cultural hall has been replaced. (completed)
The outlets through out the building all tested good.
FBJ29868 I verified the mulch - Southern Yard - was done and looks real good. (completed)
FBJ29813 I noticed the classroom table has been repaired with a new leg in room 107. (completed)
I took apart the fire alarm sensor in the kitchen and cleaned it by blowing it out, it should be working good now.
I checked the chapel and cultural hall high lights and they were all working good.
I took apart the switch for the basketball goal and there was a wire off. I had to repair it by bending the wire to screw on the switch and tightening it back up. I tested both basketball goals by lowering them up and down and they are working properly. (completed)
I lubricated the pulpit control and checked the fuse, satellite and sound system and all sounds good.
FBJ29804 I installed the soap dispensers in the kitchen, restroom and the sacrament prep room in the Cartersville building. (completed)
FBJ29804 I installed the new soap dispensers in the restroom and kitchen at the Stake Office. (completed)
worked 8 hours
Jeff
FBJ29757 I was able to repair the outlet shortage by tightening the loose wire on the inside of the outlet, by the custodial room. (completed)
I checked the thermostat controls in the building and all were working good with cool air.
FBJ29765 The cracked pipe in the parking lot facing the road had to be repaired by cutting about 3 inches off the end of the pipe where it was cracked. (completed)
I checked the screws on the changing tables and they are all good and tight to the wall.
FBJ29443 I checked the won-door handles and it has not been repaired.
FBJ29024 I noticed the carpet in the hallway and cultural hall has been replaced. (completed)
The outlets through out the building all tested good.
FBJ29868 I verified the mulch - Southern Yard - was done and looks real good. (completed)
FBJ29813 I noticed the classroom table has been repaired with a new leg in room 107. (completed)
I took apart the fire alarm sensor in the kitchen and cleaned it by blowing it out, it should be working good now.
I checked the chapel and cultural hall high lights and they were all working good.
I took apart the switch for the basketball goal and there was a wire off. I had to repair it by bending the wire to screw on the switch and tightening it back up. I tested both basketball goal by lowering them up and down and they are working properly. (completed)
I lubricated the pulpit control and checked the fuse, satellite and sound system and all sounds good.
FBJ29804 I installed the soap dispensers in the kitchen, restroom and the sacrament prep room in the Cartersville building. (completed)
FBJ29804 I installed the new soap dispensers in the restroom and kitchen at the Stake Office. (completed)
No comments:
Post a Comment