05.11.11 DALLAS

On Wednesday I went to Dallas to do the following work orders and maintenance work in the building.

I checked the thermostat controls in the building and all are working properly with cool air.

The water fountain definitely needs to replaced. I will have to pick them up at the Douglasville building from the shed and the next time I go there I will replace it.

The light ballast was out by room M-101 and 107 in the Hallway. I replaced the ballast in each light and they are working properly.

FBJ29800 I will have to check around and see where concrete parking stops can be purchased.

FBJ29829 I replaced the high light in the cultural hall 3. All other lights are working properly. (completed)

FBJ29830 I replaced the bulb in the can light that was burnt in the chapel and all other lights are working good. (completed)

I lubricated the pulpit control and checked the fuse, satellite and sound system, all sound good.

FBJ29558 I checked on the locker cabinets in the RS room and it seemed like the handles and locks have been installed. (completed)

The exit sign in the hallway was pulling apart and I had to repair it by using adhesive spray and glueing it back together.

FBJ29865 I verified the mulch - Southern Yard - is done and looks good. (completed)

FBJ29831 I had some caulking with me and I was able to repairs some of the cracks in the surfaces. I need to investigate future repairs that are needed.

worked 8 hours

Jeff







I checked the thermostat controls in the building and all are working properly with cool air.




The water fountain needs to replaced. I will have to pick them up at the Douglasville building from the shed.








The light ballast was out by room M-101 and 107 in the Hallway. I replaced the ballast in each light and they are working properly.




FBJ29800 I will have to check around and see where concrete parking stops can be purchased.





FBJ29829 I replaced the high light in the cultural hall 3. All other lights are working properly. (completed)







FBJ29830 I replaced the bulb in the can light that was burnt in the chapel and all other lights are working good. (completed)




I lubricated the pulpit control and checked the fuse, satellite and sound system, all sound good.




FBJ29558 I checked on the locker cabinets in the RS room and it seemed like the handles and locks have been installed. (completed)





The exit sign in the hallway was pulling apart and I had to repair it by using adhesive spray and glueing it back together.




FBJ29865 I verified the mulch - Southern Yard - is done and looks good. (completed)

















FBJ29831 I had some caulking with me and I was able to repairs some of the cracks in the surfaces. I need to investigate future repairs that are needed.