On Thursday I went to the Newnan building to do the following work.

I sprayed the hinges and door closures with WD40 on the interior and exterior doors through out the building to lubricate them and stop them from squeaking.

Richard asked me to repair the font area by the door where it was cracking real bad by the corner on the sheet rock. I had to dig the old mud out. Then I had to re-mud it and let it dry. Tomorrow I will sand it down and paint it.

In room 105 I painted the second coat of paint on the walls and peeled all the tape off that was around the wood trim and other areas. I put all the pictures back on the walls. I also had to move two medal cabinets back against the wall.

Worked 8 hours,

Jeff









I sprayed the hinges and door closures with WD40 on the interior and exterior doors through out the building to lubricate them and stop them from squeaking.








In the font area by the door it was cracking real bad by the corner and I had to dig the old mud out. Then I had to re-mud it and let it dry. Tomorrow I will sand it down and paint it.









In room 105 I painted the second coat of paint on the walls and peeled all the tape off that was around the wood trim and other areas. I put all the pictures back on the walls. I also had to move two medal cabinets back against the wall.